Works 2020
Works2020 Work report for Dixence Resort Spa and Hotel Centre in Hérémence: the first highlight of 2020 was undoubtedly the installation of the modular chalets
Prospecting drilling for thermal water – Combioula
Wellness, WorksAs part of the construction of the Dixence Resort Thermal Centre, La Foncière de la Dixence SA has mandated BEG SA Géologie & Environnement to monitor prospecting drilling intended to define the existing thermal water reservoir in Combioula
The installation of prefabricated guestrooms
WorksWork report for Dixence Resort project: installation of prefabricated timber hotel rooms
Works 2019
WorksWe have now completed the first two apartment buildings : Aiguilles Rouges & Tête Blanche, which is an achievement in itself, and establishes the architecture of the complex, allowing one to imagine the sense of place that will be created by the whole.
Prefabricated timber hotel rooms – modubois sa
WorksWhile construction works were going full tilt on site, the timber hotel bedrooms were under fabrication in a workshop, and are now completely finished, bathrooms and all and ready to be lifted into place and “plugged in” in Hérémence.
Progress report
Uncategorized, WorksWe broke ground at the end of 2016.
Little by little the excavation work started to change the form of the landscape, with slopes and terraces creating the seat from which the thermal centre and hotel complex could evolve.